Palimar Matha · Haridwar, IndiaNature Conservation & Ecological Stewardship● Active

Bade Hanuman Mandir Solar Project

A 35 kW hybrid solar system, expandable to 70 kW or 140 kW, paired with heat-pump water heating for the Goshala and pilgrim facilities at Bade Hanuman Mandir. It's projected to cut electricity costs by up to 93% and offset 30 tons of CO₂ a year.

Donate to this project →
Bade Hanuman Mandir · Haridwar · proposed solar array
35 kW
Hybrid solar capacity
84-93%
Electricity cost reduction
30 tons
Annual CO₂ offset
100
Gir cows sheltered

About this project

The Bade Hanuman Mandir campus in Haridwar currently draws 7 to 8 kW from the grid, and planned expansion will push that demand higher. Electricity is already the campus's largest recurring cost, and a solar system sized for that load is the clearest way to bring it down and move the campus toward energy independence.

The Mandir sits on the banks of Mother Ganga and runs several ongoing programs: community feeding (Annadaan) for ascetics, pilgrims, and the economically disadvantaged; Gau Seva, which shelters and cares for indigenous cows; housing for visiting devotees; and the discourses and traditional education that preserve Vedic knowledge. All of it runs on the same grid connection, so a power failure or a rate hike affects everything at once.

In Uttarakhand, solar does more than cut bills. It reduces dependence on a grid that carries real risk. Despite abundant hydropower, the state still draws thermal power (coal and gas) from the national grid, so on-site solar cuts carbon emissions at the source. Himalayan hydropower construction also carries hazards in this tectonically active, ecologically fragile region (Seismic Zones IV and V): tunnelling and blasting destabilize slopes and raise landslide risk, construction debris was identified by experts as a factor in the 2013 Kedarnath disaster, and river diversion damages aquatic ecosystems. Decentralized solar sidesteps that risk and gives the campus a stable, locally generated supply.

The project installs a 35 kW Solar Hybrid System (expandable to 70 kW or 140 kW) alongside an energy-efficient heat-pump water-heating system for the kitchens and devotee facilities. The total project cost is ₹53,20,000 (approx. $61,149): ₹40,35,000 ($46,379) for the solar hybrid system, ₹8,50,000 ($9,770) for the heat pump, and ₹4,35,000 ($5,000) for associated construction not covered by the equipment installation.

The payoff goes beyond the electricity bill: added resilience against grid failures and regional disasters, a cost cut of 84 to 93%, roughly 30 tons of CO₂ offset a year, and support for Agri-PV integration with the Mandir's cultivation work. Over its operating lifetime, the system is projected to save more than ₹1.1 crore (approx. $126,437), money that can go toward Dharmic activities instead of power bills.

This appeal asks for the full project cost of ₹53,20,000 (approx. $61,149) for the Haridwar initiative. We document and report on every stage.

Sustenance Impact Report

Over its operating lifetime, this system is projected to save more than ₹1.1 crore (approx. $126,437) in electricity costs while supporting the campus's growth. It's a long-term investment in the Matha's self-sufficiency on the banks of Mother Ganga.

Media gallery

Saransh Charitable Foundation
Saransh Charitable Foundation
Saransh Charitable Foundation
Saransh Charitable Foundation
Saransh Charitable Foundation
Saransh Charitable Foundation

Progress timeline

  1. May 23, 2026

    Board grant approval

    Initial $13,000 reserved from SCF US for site survey, vendor onboarding, and partial deposit.

  2. Jun 04, 2026

    FCRA partner engaged

    Samskrita Bharati National Office confirmed as the domestic remittance channel.

  3. Jul 12, 2026

    Vendor selection & site survey

    Three certified solar EPC contractors evaluated; final selection pending board ratification.

  4. Sep 2026

    Panel mounting & hybrid inverter install

    Civil works on rooftop mounting structure followed by panel deployment.

  5. Oct 2026Upcoming

    Commissioning & first-year monitoring kit

    Live energy production data piped into project page after grid synchronization.